An engineering change request records a proposed change to a controlled design or process. It should identify the currently released revision, explain the problem and proposed fix, and show what will happen to stock, work in progress and instructions if the change goes ahead. The decision should say which changes it authorizes and who must verify the result.

Keep the request open through implementation. Approval to proceed answers whether to make the change. Release identifies which revised documents can be used and from when. Closure records the first affected lot, the disposition of existing stock and the checks that were actually done. Some teams use an engineering change order (ECO) for the authorized release instructions. Use your organization’s terminology consistently and retain the link between request, decision, release and evidence.

One request, from problem to first production lot

Fictitious example · ECR-026 · MB-17 mounting bracket. At final assembly, the screw head on line 2 interferes with a guide on drawing MB-17 revision B. Engineering proposes moving one mounting hole by 2 mm on draft revision C. Hole diameter and material stay the same. Trial measurements and the marked-up draft go with the request. Revision B remains the released drawing while C is in review.

Production: 40 finished B brackets and 12 B units in progress. Production proposes finishing the 12 under the existing B work order and using B stock only for assemblies confirmed compatible with B. Keep B and C stock separately identified. Quality: inspect the changed dimension and verify fit on the first C unit before releasing the lot. Engineering: revise the drawing and work instruction, and confirm who is responsible for the fixture change.

Decision: proceed on line 2 for the named assembly only. Release: drawing MB-17 C and work instruction WI-23 D take effect from lot L-104, after the fixture and first-piece checks pass. Closure: record the actual first C lot, first-piece report and who verified the B stock segregation. If the trial fails, hold L-104, keep C out of the production instructions and return the affected change package for review.

Fields to put on the engineering change request form

Field group What to record
Identity and scope Request ID, title, requester, owner, site or line, part or process ID, current revision, and links to affected drawings and instructions. Record other assemblies or sites only if they are in scope.
Problem and proposed change Where the issue occurs, evidence, proposed change, and what will stay the same. Record quantities and units with measurements. Add a marked-up copy where a drawing comparison matters.
Impact findings Separate fields for Design, Production and Quality. Add Supply or Service when applicable. Record tooling, stock, work in progress, supplier orders, inspection, compatibility, and affected work instructions. A finding of “no impact” needs a reason. Unchecked items stay open.
Decision Approve to proceed, return for information, reject or defer, with who decided, when, the reason, and the exact scope and evidence reviewed. Record conditions separately from a completed release.
Release and effective point List the authorized drawing, instruction and inspection revisions. Specify the effective date, lot, batch, serial range or work order and any prerequisites. Identify who removes outdated copies at the point of use.
Implementation and closure Record actual first affected unit or lot, disposition of old stock and work in progress, verification results, evidence links, closure decision and closure date. Leave these blank until the actions occur.

Give reviewers questions they can answer

Ask Engineering to confirm dimensions, affected parts and compatibility. Ask Production where old and new work can get mixed: stock labels, open work orders, fixtures, machine settings, and work instructions. Ask Quality what must be checked before release and who will sign off the result. If an open purchase order is affected, bring in the buyer before a supplier uses the revised drawing. For material impacts that extend beyond the approved scope, start another review before releasing the affected work.

Set the cutover at a boundary someone on the floor can identify. “From next week” is hard to apply to an order already in progress. “From lot L-104 once the checks pass” gives the supervisor a point to verify. If the lot changes, record the new effective point and its authorization. A confirmed change to an earlier lot should also reach the people who received the old instructions.

The NASA systems engineering handbook’s configuration management guidance is a useful example of separating the proposal, impact evaluation, decision and implementation. Use the controls appropriate to your product, customer agreements and organization.

Set up the change record and the drawing release in Folderit

  1. Start with a template for the request. Under Admin tools → Form templates, create an Engineering Change Request eForm. Use short text for part and baseline revision, long text for the proposed change and each finding, a user field for the owner, and a list for a maintained progress status. Use date fields where useful, plus a separate field for lot or work order. Require the intake details. Leave actual release and closeout details for the people performing those steps. The Tailor plan includes eForms and the Workflow Designer.
  2. File the supporting material where the right people can open it. Attach a marked-up copy to the request or keep it in a working area, with the current released document clearly identified. For a centrally managed drawing, the Related items controls can connect a file to the form record. Verify access on both sides with the actual reviewer’s permissions. A link in the record does not give someone access to the underlying file.
  3. Collect findings before requesting the decision. Open the form record’s Workflow menu. Add the Design, Production and Quality recipients with Fill fields. Show each person the baseline, scope and supporting information. Give them edit access to their assigned finding fields within the task. Parallel tasks can collect independent findings; when all are needed, check the configured completion requirement. After reviewing those findings, start the approval or use a configured stage that places approval after field completion. The coordinator records the next status after checking the workflow outcome.
  4. Verify the revision separately at release. Keep a proposed revision away from the view production relies on until your release controls are ready. In Folderit, uploading a new file version makes it current. The earlier approval stays with the earlier version, and the Versions list shows which version a task belongs to. Send the revised file for its own approval when required and verify the copy the production team can open. Authorizing the eForm request does not configure a manufacturing cutover or update an ERP, a fixture, or an active work order.
  5. Record the result from the floor. When Quality and Production have checked the first unit and stock disposition, collect the actual lot, date, evidence and exceptions in a separate closeout section. Add any missed actions to the next review or keep the change open. Show owner, part, decision status and effective point in the folder’s list view so the coordinator can spot work that has approval but still lacks release or implementation evidence.

Before adopting the template, run a clean approval and a failed first-piece check with sample records. Check that each reviewer can open the exact supporting file, that the decision identifies the revision and lot, and that the production role sees the correct released copy in both cases. Repeat the test for a new revision uploaded while the earlier version is in approval. The example above uses documented features; the combined configuration has not been tested on a live production workflow. For the wider repository setup, see Folderit’s guide to drawings, versions and approvals and its engineering document control features.